2017-2019
Structure of the CDU / VDU complex. Gazprom Neft Omsk Refinery
Corrosion Protection and Fire Protection
Deep processing depth ~100%. Complex with a capacity of 8.4 million tons of oil + 1.2 million tons of condensate/year. Launched in 2023, replaced 6 obsolete units. Solar power plant (1.2 MW). "Biosphere" biological treatment complex with a closed water cycle.
Products:
- TRIOCOR™ ZINC 1700
- TRIOCOR™ MASTIC 4500
- TRIOCOR™ FINISH 5500
- TRIOTHERM™ 3500
- TRIOTEMP™ 400
- TRIOTEMP™ 600
- TRIOCOR™ RVS 9510
Coverage:
624,000 m²
Asset Owner:
JSC Gazpromneft – ONPZ
#Oil & Gas