2019
Ensuring the needs of Amur Gas Processing Plant. Amur Thermal Power Plant
Corrosion Protection and Fire Protection
Products:
- TRIOCOR™ MASTIC 4500
- TRIOFLAME™ AK 7700
- TRIOTHERM™ 3700+TRIOFLAME™ AK 7700
- TRIOCOR™ FINISH 5500
List of Works:
- Fire protection design
- Supply of materials
- Application of fire protection and corrosion protection materials
Coverage:
40 000 м²
Asset Owner:
LLC Gazprom Pererabotka Blagoveshchensk
General Designer:
JSK Institute Teploelectroproject
General Contractor:
JSC TEK Mosenergo
Contractor:
LLC GEH Engineering
Subcontractor:
O3 Company
#Power Generation